National Assembly Chairman Tran Thanh Man inspected the Phu Quoc International Airport expansion project, Provincial Road DT.975 and Phase 1 of the urban rail project, as well as APEC Boulevard and the APEC Convention Centre project.
At the project sites, National Assembly Chairman Tran Thanh Man and the working delegation conducted field inspections and heard progress reports from project owners and contractors. He also encouraged and presented gifts to workers carrying out construction on the projects.

National Assembly Chairman Tran Thanh Man and the working delegation inspect APEC projects and speak with Dang Minh Truong, Chairman of Sun Group. (Photo: Hai Duy)
According to leaders of the An Giang Provincial People’s Committee, preparations for the APEC Economic Leaders’ Meeting have been identified by the province as a particularly important political and diplomatic task, as well as a strategically significant opportunity to improve infrastructure, upgrade the urban landscape and create new development potential for Phu Quoc.
To date, 21 projects serving APEC 2027 are under implementation. A number of key projects and components have achieved positive progress: the runway at Phu Quoc International Airport has been completed, while terminal facilities, the APEC Convention Centre, Provincial Road DT.975, Phase 1 of the urban rail line and technical infrastructure projects are being accelerated.
According to a report by the An Giang Provincial People’s Committee, the province remains fully aware that a substantial volume of work is still outstanding, time is limited and progress varies among projects. The current management focus is therefore on closely monitoring each critical path, interim milestone and input condition, particularly land clearance, construction materials, technical infrastructure, legal procedures and construction resources. At the same time, project owners, investors and contractors are required to proactively prepare schedule-recovery plans, increase manpower and equipment, and organise construction appropriately.
An Giang’s position is that progress must go hand in hand with quality, safety, efficiency and long-term sustainability after investment. “The province’s objective is not only to successfully fulfil the requirements of hosting APEC 2027, but also to ensure that resources invested for the event are utilised effectively and sustainably over the long term, truly becoming a new driver of development for Phu Quoc in particular and An Giang Province as a whole,” the report stated.

One of the projects serving APEC in An Thoi, Phu Quoc. (Photo: Anh Duong)
How Are the Projects Progressing?
Of the 21 projects serving APEC 2027, 11 are public investment projects currently being implemented on schedule, with completion expected in stages from November 2026 to 30 June 2027. Among them, Phase 1 of the urban rail line has the largest investment, at VND 4.511 trillion. The route is approximately 17.7 km long, with 5–7 stations and one depot. It has a design speed of 70–100 km/h and will operate trains of 3–5 carriages. The project is being developed by Sun Phu Quoc Co., Ltd. and has disbursed VND 3.132 trillion, equivalent to 69.43% of the planned capital.
The second-largest project by investment is Provincial Road DT.975, which is 19.26 km long and designed with 10 traffic lanes. The project includes four bridges, eight intersections and synchronous infrastructure. Disbursement has reached VND 1.307 trillion out of VND 2.304 trillion, equivalent to 56.72%.

National Assembly Chairman Tran Thanh Man and Deputy Prime Minister Pham Gia Tuc present gifts to engineers and workers at the APEC Convention Centre. (Photo: Hai Duy)
For the 10 PPP and business investment projects, Sun Phu Quoc Co., Ltd. is also the developer of the Nui Ong Quan mixed-use eco-tourism urban area, which includes low-rise housing, healthcare and educational facilities, among other components, with a total investment of VND 5.55 trillion.
Sun Phu Quoc Co., Ltd. is also the developer of the APEC Convention Centre, with an investment of VND 21.86 trillion. The centre comprises three above-ground floors and one basement level, with a minimum capacity of 6,500 people; a multi-purpose theatre with six above-ground floors and one basement level, accommodating around 4,000 people; as well as APEC Park and a technical infrastructure system.
The Phu Quoc International Airport expansion project, developed by Sun Airport Corporation, has a total investment of up to VND 22 trillion and includes the construction of a runway, Terminal T2 and a VIP terminal. The developer has disbursed VND 14.875 trillion, equivalent to 67.6% of the total, with completion expected between September and December 2026.